Blowing Rock House: Laying the Foundation April 2011
Blowing Rock House: Framing June 2011
Blowing Rock House: Framing August 2011
Blowing Rock House: Framing August 2011
Blowing Rock House: Framing walls and ceiling September 2011
Blowing Rock House: Siding September 2011
Blowing Rock House: Laying block and installing flue liners for fireplace September 2011
Blowing Rock House: Bark Siding October 2011
Blowing Rock House: Board and batten siding October 2011
Blowing Rock House: Siding October 2011
Blowing Rock House: Installing timbers November 2011
Blowing Rock House: Roofing December 2011
Blowing Rock House: Stone wall January 2012
Blowing Rock House: Block and stone at chimney/fireplace January 2012
Blowing Rock House: Stone retaining wall January 2012
Blowing Rock House: Stone at patio February 2012
Blowing Rock Addition: Framing addition June 2011
Blowing Rock Addition: Framing Bump-outs June 2011
Blowing Rock Addition: Framing June 2011
Blowing Rock Addition: Siding and Framing Chimney August 2011
Blowing Rock Addition: Forming ends of Retaining Wall September 2011
Blowing Rock Addition: Sheeting October 2011
Blowing Rock Addition: Sheeting October 2011
Blowing Rock Addition: Removing existing wall October 2011
Blowing Rock Addition: Trimming windows October 2011
Blowing Rock Addition: Cedar shake siding November 2011
Blowing Rock Addition: Siding November 2011
Blowing Rock Addition: Siding painted December 2011
Blowing Rock Addition: Framing header January 2012
Blowing Rock Addition: Digging footers January 2012
Blowing Rock Addition: Timbers January 2012
Blowing Rock Addition: Laying block January 2012
Blowing Rock Addition: Laying stone at the fireplace January 2012
Blowing Rock Addition: Laying stone at BBQ February 2012
Blowing Rock Addition: BBQ area February 2012
Blowing Rock Addition: BBQ nearing completion February 2012
Blowing Rock Addition II: Demo September 2011
Blowing Rock Addition II: Demo September 2011
Blowing Rock Addition II: Pouring footers October 2011
Blowing Rock Addition II: Laying block October 2011
Blowing Rock Addition II: Framing bump-out October 2011
Blowing Rock Addition II: Bond beams October 2011
Blowing Rock Addition II: Framing November 2011
Blowing Rock Addition II: Deck framing November 2011
Blowing Rock Addition II: Interior framing December 2011
Blowing Rock Addition II: Interior framing December 2011
Blowing Rock Addition II: Roof framing January 2012
Blowing Rock Addition II: Deck framing February 2012
Blowing Rock Addition II: Bark siding January 2012
Yonahlossee Deck: Railing fabrication and installation December 2011
Yonahlossee Deck: Finished December 2011
Yonahlossee Remodel: Framing after demolition February 2012
Blowing Rock Remodel: Framing new ceiling and skylight February 2012